Schedule Detail Terms & Tasks

Created by Privv Support, Modified on Fri, 10 Mar, 2023 at 4:48 PM by Privv Support

ScheduleTasks
Project Development Plan
Create financial model or Pro-Forma
Identify funding sources and applicable uses
Develop and structure procurement contracts
Define and initiate process for selection of design team
Define and initiate process for selection of construction team
Develop project budget estimate
Identify method of construction delivery
Create milestone project schedule
Financial Plan
Establish a detailed project budget
Ensure eligible expenditures are funded from appropriate sources
Maintain client compliance with its obligations to respective funding agency
Property Analysis
Identify Property Location
Identify street address nearest transit interstate specialized intersection
Catalogue area context with narrative and photos
Note existing land uses with 1/2 to 1 mile
Identify potential issues (environmental noise access restrictions etc.)
Identify building and development characteristics use types building heights development density
Catalogue all offsite improvements (roadways curb cuts transit stops utilities etc.)
Catalogue all on-site improvements (utilities topography environmental)
Obtain county Assessors Records
Obtain available records of ownership
Identify need for lot split or parcel consolidation
Identify jurisdictional official (national state county city local University etc.)
Catalogue Zoning History (historical files general plan area plan zoning maps etc. )
Catalogue City Engineering Records (Quarter section maps city utility maps private utility records)
Generate Property Analysis Report of Findings (Exhibit B)
Due Diligence
Determine property valuation
Review Phase I Environmental
Review Phase II (If applicable)
Obtain ALTA Survey
Obtain Title Report
Obtain purchase agreements settlement documents affidavits
Property Acquisition
Property analysis and value determination
Obtain required entitlements appraisals tenant relocation and items nectary to acquire control of the project site
Coordinate property acquisition and relocation in compliance with federal state and city requirements
Develop Project Management Plan
Define programming requirements
Create plan for fulfilling requirements
Establish Project Criteria
Develop Project Procedures Manual
PPM - Budget and cost control monitoring
PPM - Project schedule development maintenance and reporting
PPM - Project methods and procedures - Bidding
PPM - Project methods and procedures - Pay requests payment format and frequency
PPM - Project methods and procedures - Change orders – design and construction
PPM - Project methods and procedures - Submittals
PPM - Project methods and procedures - Correspondence
PPM - Project methods and procedures - Reports
PPM - Project methods and procedures - Closeout
PPM - Correspondence distribution
PPM - Meeting type and frequency
PPM - Design review process & procedure
PPM - Decision authority
PPM - Project acceptance & closeout
Program (Programming Phase)
Program - Achieve Program Approval
Initial Project Schedule
Refine Project Schedule
Initial Project Estimate (Budget)
Update concept estimate with probably costs
Review budgeted costs and exclusions
Receive approval of concept estimate
Initial Project Cash Flow
Develop draft Cash Flow & Financing model for review
Receive approval of Cash Flow
Consultant RFP Phase
Develop and solicit RFP (Exhibit C)- Architectural Structural MEP Landscape
Evaluate (Exhibit D) - Architectural Structural MEP Landscape
Develop and solicit RFP (Exhibit C)- Civil Engineering and Surveying
Evaluate (Exhibit D) - Civil Engineering
Develop and solicit RFP (Exhibit C)- Traffic Engineering
Evaluate (Exhibit D) - Traffic Engineering
Develop and solicit RFP (Exhibit C)- Geotechnical Engineering
Evaluate (Exhibit D) - Geotechnical Engineering
Develop and solicit RFP (Exhibit C)- Signage Consultant/Contractor
Evaluate (Exhibit D) - Signage Consultant
Develop and solicit RFP (Exhibit C)- Low Voltage – Security audio video IT
Evaluate (Exhibit D) - Low Voltage - Security audio video IT
Develop and solicit RFP (Exhibit C) - Materials Testing
Evaluate (Exhibit D) - Materials Testing
Consultant Awards & Negotiations
Award - Architectural
Award - Civil Engineering and Surveying
Award - Traffic Engineering
Award - Geotechnical Engineering
Award - Signage Consultant
Award - Low Voltage - Security audio video IT
Award - 3rd Party Peer Reviewer
Award - Materials Testing
Contract Final - Design Team
Execute Contract - Architectural
Execute Contract  - Civil Engineering and Surveying
Execute Contract  - Traffic Engineering
Execute Contract  - Geotechnical Engineering
Execute Contract  - Signage Consultant
Execute Contract  - Specialty Graphics
Execute Contract  - 3rd Party Peer Reviewer
Execute Contract  - Materials Testing
Update Project Org. Chart
Update Project Management Plan (PMP)
Update Project Procedures Manual (PPM)
Basis of Design (BOD)
Develop Basis of Design
Basis of Design Approval
Review Basis of Design provide redlines comments edits
Receive Basis of Design Approval
Update Project Management Plan (PMP)
Concept Design
Schedule Design Meetings and work sessions
Document and publish Design Meeting Minutes
Publish Concept Plans for review
Receive approval to proceed to SD Phase
50% Schematic Design
Develop 50 SD Set
Publish 50% SD Set
Review 50% SD for compliance with BOD
Review 50% SD for Budget compliance
Receive approval to proceed to 100% SD
100% Schematic Design
Develop 100% SD Set
Publish 100% SD Set
Perform 100% SD Estimate
Review 100% SD A/E deliverable for contract compliance
Facilitate design progress review with AHJ (e.g. Permitting)
Publish necessary corrections for BOD & 100 SD Deliverable
Receive approval to proceed to DD Phase
Value Engineering Review I (30%)
Schedule Value Engineering work sessions
Receive approval of CML to proceed with design revisions
Project Budget Update & Approval
Update Project Budget with Target CML
Receive approval of updated Project Budget
50% Design Development
Develop 50% DD Set
Publish 50% DD Set
Perform 50% DD Estimate Compare to CML
Review 50% DD for compliance with BOD & CML
Receive approval to proceed to 100% SD
100% Design Development
Develop 100% DD Set
Publish 100% DD Set
Perform 100% DD Estimate
Review 100% DD for compliance with BOD & CML & AHJ
Review 100% DD A/E deliverable for contract compliance
Facilitate design progress review with AHJ (e.g. Permitting)
Publish necessary corrections for BOD & 100 SD Deliverable
Receive approval to proceed to CD Phase
Value Engineering Review II (75%)
Update Cost Management Log \CML\ (Value Engineering)
Schedule Value Engineering work sessions
Receive approval of CML to proceed with design revisions
Project Budget Update & Approval
Receive approval of updated Project Budget
50% Construction Document Design
Develop 50% CD Set
Publish 50% CD Set
Perform 50% CD Estimate Compare to CML
Review 50% CD for compliance with BOD & CML & AHJ
Receive approval to proceed to  90% CD
90% Construction Document Design
Develop 90% CD Set
Publish 90% CD Set
Perform 90% CD Estimate
Review 90% DD for compliance with BOD & CML & AHJ
Facilitate design progress review with AHJ (e.g. Permitting)
Publish necessary corrections for BOD & 100 SD Deliverable
Receive approval to proceed to Permit Phase
Permit Review
Develop Permit set
Publish Permit Set
A/E Submit plans for Permit Review
Schedule status update meetings (A/E & Permit Review Team)
Perform Permit Set Cost Estimate
Publish necessary corrections for CML BOD AHJ (Permit revisions)
Project Budget Update & Approval
Receive approval of updated Project Budget
100% Construction Document Design
Develop 100% CD Set
Publish 100% CD Set
Submit 100% CD Set for Permit Approval
Review 100% CD for compliance with BOD & CML
Review 100% CD A/E deliverable for contract compliance
Publish necessary corrections for BOD CML Issue for Construction Set
Receive approval to proceed to CD Phase
Permit Approval
Receive Permit Approval from AHJ
Update and Publish Stamped IFC Set
Issued For Construction Design
Publish IFC Set
Construction Management RFP Phase
Confirm method of procurement (CM)
Pre-Qualify Candidates
Develop scoring & award criteria (Exhibit E)
Develop and solicit RFP for CM Services
Receive RFP Proposals
Review proposals and request clarifications (if needed)
Hold CM Interviews and Presentations
Prepare bid analysis for review
Construction Management
Award & Negotiations
Recommend for Award CM
Receive approval to Award
Notify CM of Award
Commence Contract Negotiations
Receive approval to make edits
Revise/Update contract
Contract Final - Construction Manager
Update and Publish Final Contract
Execute Contract - Construction Manager
Distribute Contract for record
GMP Review Phase
CM Issue GMP Proposal
Review CM GMP Proposal
Revise & Update GMP Proposal
Recommend for Approval to Client (GMP)
Budget Update & Approval
Present updated Project Budget and Schedule to Client for review
Receive approval of Updated Project Budget and Schedule incorporating GMP
Receive approval from Client to proceed with NTP and commence work
GMP Approval & Contract Amendment
Execute Amendment to CM Agreement incorporating GMP
Update Master Budget and Cash Flow
Update Master Schedule
Update Project Management Plan (PMP)
Update Project Procedures Manual (PPM)
Notice To Proceed (NTP)
Issue Formal Notice to Proceed to CM
Project kick-off meeting (Intro team members roles & responsibilities)
Project kick-off meeting (site logistics safety protocols site safety plan)
Establish SWPPP permit plan and requirements
Establish contractor's proof of insurance and bonds
Ground Breaking Ceremony If Applicable
FF&E Procurement Phase
Develop and solicit RFP - Signage
Evaluate RFP
Award RFP Contracts
Execute contract
Develop Furnish and Installation Schedule
Testing and commission
FF&E Awards & Negotiations
Award - Signage
Award - Sponsorship Signage & Branding
Award - Food Service Equipment
Award - Facility Operations
Award - Team Operations
Award - Specialty Lighting / Sports Lighting
Award - Field / Event Surface
Award - Furnishings
Award - Fixed and Loose Seating
Award - Technology (DAS & WIFI)
Award - Technology (Converged Network)
Award - Technology (Audio System)
Award - Technology (Video Displays)
Award - Technology (Video Displays - Marquee)
Award - Technology (Video Production)
Aware - Technology (Broadcast Cabling)
Award - Technology (IPTV)
Award - Technology (TV Displays)
Award - Technology (POS)
Award - Technology (Security)
Furnish & Install - FF&E
Furnish & Install - Signage
Furnish & Install - Sponsorship Signage & Branding
Furnish & Install - Food Service Equipment
Furnish & Install - Facility Operations
Furnish & Install - Team Operations
Furnish & Install - Specialty Lighting / Sports Lighting
Furnish & Install - Field / Event Surface
Furnish & Install - Furnishings
Furnish & Install - Fixed and Loose Seating
Furnish & Install - Technology (DAS & WIFI)
Furnish & Install - Technology (Converged Network)
Furnish & Install - Technology (Audio System)
Furnish & Install - Technology (Video Displays)
Furnish & Install - Technology (Video Displays - Marquee)
Furnish & Install - Technology (Video Production)
Furnish & Install - Technology (Broadcast Cabling)
Furnish & Install - Technology (IPTV)
Furnish & Install - Technology (TV Displays)
Furnish & Install - Technology (POS)
Furnish & Install - Technology (Security)
Mobilization
Site Office Set-Up
SWPPP Installation
Site Mobilization
Construction Phase (0 - 25%)
Construction Progress 25%
Review Construction progress & contingency reserve
Update Master Budget & Schedule
Receive approval for Updated Master Budget & Schedule
Construction Phase (25 - 50%)
Construction Progress 50%
Review Construction progress & contingency reserve
Update Master Budget & Schedule
Receive approval for Updated Master Budget & Schedule
Construction Phase (50 - 75%)
Construction Progress 75%
Review Construction progress & contingency reserve
Update Master Budget & Schedule
Receive approval for Updated Master Budget & Schedule
Construction Phase (75 - 100%)
Construction Progress 100%
Review Construction progress & contingency reserve
Update Master Budget & Schedule
Receive approval for Updated Master Budget & Schedule
Comissioning & Training
Initial Commissioning Review & Inspections
Issue corrective reports
Field corrections
Finalize Commissioning for Sign Off
Substantial Completion
AHJ Inspections
Life Safety Inspections
Health Department Inspections
A/E Inspections
CM field corrections following inspections
Approval of Inspections
Issuance of Temporary Certificate of Occupancy (TCO)
Receive Architect of Record - Substantial Completion Form
Issuance of Post Construction Check List (Exhibit K)
Issuance of Punch List
Certificate of Occupancy
Finalize Post Construction Checklist (Exhibit K)
Schedule and distribute post-construction activities and completion
Complete Punch List work
Finalize TCO action items for issuance of Certificate of Occupancy (CO)
Occupancy & Move-In
Receive CO
Closeout
CM Submit Closeout Package for review
Review of Closeout Package
Receive Attic Stock
Schedule 12-month warranty walk through (11-months after SC)
Approval of Closeout Package
Final Payments
Reconciliation of total Project Costs and Contracts
Update Project Budget and Schedule
Receive approval for Updated Master Budget & Schedule
Issuance of Final Payments
Historical Data (Privv)
Compile all project data and costs for Privv Historical
Update and finalize Final Project Report (reconcile PMP PPM)
Compile all project data and costs for Privv Historical

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article